Level One schedule and milestone analysis

A management-level schedule built as a working application: swimlanes for each part of the project, bars labeled with their start and finish milestones, the ties between them, and the milestone history behind each date.

Problems this solves

What the work covers

Level One applications

Swimlanes, labeled bars, relationship ties with type and lag, scale switching, logic trace and comparison with BL or BL1.

Milestone variance

Milestones at Levels 1, 2 and 3 against BL, BL1 and BL2, with the three variances and the reason each moved.

Schedule reserve

The margin between the forecast and a contractual date, counted in working days and tracked update to update.

Cost contingency

Kept as a separate dollar balance, with any exhaustion forecast built only from a time-phased list of expected draws.

Typical deliverables

How the work runs

  1. Agree the summary structure. Workstream lanes, the start and finish milestone for each bar, and the ties that matter at Level One.
  2. Link milestones to the detailed schedule. So each Level One date comes from the working schedule, not a drawing.
  3. Track reserve and contingency. Schedule reserve in working days to the contractual date; cost contingency as a separate dollar balance.
  4. Present and review. Present mode for the meeting room; Review mode with BL and BL1 comparison for the working session.

See a working demonstration

Each demonstration opens on the home page with a fictional project and synthetic data. Sort, filter and drill into the records.