4D construction scheduling and visualization
Schedule activities linked to 3D model objects, so the construction sequence can be played, paused at any data date and questioned. Select an activity to find its geometry, or an object to find its activities.
Problems this solves
- Sequencing conflicts are found in the field instead of in the planning meeting.
- Leadership reviews a Gantt chart that does not show where the work is.
- Lift plans and access constraints are hard to explain from the schedule alone.
- Progress updates need a visual that matches the reported data date.
What the work covers
Schedule-linked models
Every modeled object carries an Activity ID, so levels, disciplines and packages can be shown or hidden by schedule status.
Sequencing reviews
The planned order of work played against the data date for constructability and access reviews.
Rendered 4D videos
A narrated or captioned sequence of weekly updates for meetings and progress reports.
Update refresh
The model rebuilt from each new update, so the visual always matches the reported dates.
Typical deliverables
- Interactive 4D model linked to the schedule
- Rendered 4D sequence video
- Activity-to-object mapping table
- Sequencing review notes
Models are for planning and communication, not engineering design. The demonstrations use a fictional facility and a synthetic schedule.
How the work runs
- Agree the model scope. Which areas, levels and objects the model needs for the decisions in question.
- Link objects to activities. Each object tagged with the Activity IDs that build it.
- Review the sequence. The build played against the data date with the planners and construction team.
- Refresh with each update. The model and any rendered sequence rebuilt from the new schedule.
See a working demonstration
Each demonstration opens on the home page with a fictional project and synthetic data. Sort, filter and drill into the records.
- Open the interactive 4D modelPlay the construction sequence, select an activity to find its geometry, or an object to find its activities.
- Open the Interactive P6 Schedule demonstrationrts
- Open the Resource Histogram demonstrationWeekly craft headcount from each activity's crew and dates, current forecast against the baseline, with drill-down to theā¦
- Open the Critical Path Analysis demonstrationhealth
Watch it working
Ninety seconds of a fictional topside module built in a fabrication hall against a synthetic schedule, shown as a sequence of weekly updates with the data-date line. Fictional project, synthetic data.
What the video shows
Ninety seconds of a fictional topside module built in a fabrication hall against a synthetic schedule, shown as a sequence of weekly updates with the data-date line. The video has no narration. Percent complete is shown in the schedule table, not inside the bars.